Tarco Scope:

  • Upgrade of the station and ESD PLCs from PLC-5s to ControlLogix
  • Design, procurement, installation and integration of all existing and new instrumentation
  • Tarco acted as the primary contractor whose responsibility included coordinating and directing all engineering and on site activities
  • Replacement of all electrical cabling, MCC, Instrumentation, PLCs and HMI within a two-week outage schedule
  • All engineering, procurement, and construction was staged to ensure project completion was achieved within a very short six month timeline