Compressor Station PLC Upgrade and Rewiring (Alberta, Canada)
Compressor Station PLC Upgrade and Rewiring (Alberta, Canada)
Tarco Scope:
- Upgrade of the station and ESD PLCs from PLC-5s to ControlLogix
- Design, procurement, installation and integration of all existing and new instrumentation
- Tarco acted as the primary contractor whose responsibility included coordinating and directing all engineering and on site activities
- Replacement of all electrical cabling, MCC, Instrumentation, PLCs and HMI within a two-week outage schedule
- All engineering, procurement, and construction was staged to ensure project completion was achieved within a very short six month timeline